Middletown Paving Project 2021-22

For more information: Click Here

Paving updates as of Oct 12, 2022

Zone #6

Final asphalt surface course placement for remaining streets will be completed later this month.

Zone #7

Concrete curb and handicap ramp repairs completed.  Asphalt milling and paving has begun.  Final asphalt surface course placement will be completed by mid-December (weather permitting).

Please Note:  Glenmore Drive and Flemming Road (from University Blvd. to the dead end east of Sierra Road) will paved at later date (tentatively 2023) in conjunction with a watermain replacement project.

 Zone #8

Concrete curb and handicap ramp repairs have started.  Milling and paving will start in spring of 2023.  Expected completion summer 2023.

Zone #9

Concrete curb and handicap ramp repairs will start in early 2023 as weather permits.  Milling and paving will start in spring 2023.  Expected completion summer 2023.

Thank you for your patience and pardon our progress!

2021 - 22 Paving Levy  map Zone 6 Oct update

2021 - 22 Paving Levy  map Zone 7 Oct update

2021 - 22 Paving Levy map Zone 8 Oct update

2021 - 22 Paving Levy Zone 9 Oct update

Current Updates as of June 3, 2022 - 

 Zone #4

Final asphalt surface course placement is underway and will continue over the next couple weeks.

Zone #5 and #6

Concrete curb and handicap ramp repairs are nearly complete.  Pavement milling will begin Monday June 6th in Zone #5 and progress from east to west followed by base repair and intermediate asphalt course placement.

 Zone #7

Concrete curb and handicap ramp repairs will begin soon.

Thank you for your patience and pardon our progress!

2021 Annual Paving Program

Carryover work is being completed from last year.  This includes paving of 1st Avenue between Verity Pkwy. and University Blvd., Lefferson Road between Highland St. and Breiel Blvd. and North Ave. between University Blvd. and Shafor St.  Work will continue of the next several weeks.

March - 2022  

Work restarted on the 2021 – 22 Paving Levy Project in late March.  Asphalt milling began on Monday March 21, 2022 weather permitting in Zone #4 (see attached map). This will be followed by subgrade repairs then placement of intermediate and final asphalt courses. Work will generally start on the south side of Zone #4 then proceed north. Streets included in the project will be posted for no parking in advance. Pardon our progress!

2021 - 22 Paving Levy map of Zone 4 April update
2021 - 22 Paving Levy map of Zone 5 April update
2021 - 22 Paving Levy map of Zone 6 April update
2021 - 22 Paving Levy map of Zone 7 april update